You Submitted a Texas WSIG Application. What Happens Next?

Your WSIG application is submitted. For the moment, the instinct may be to wait and see what happens.

There is one thing worth doing immediately, though: make sure somebody is watching the email address listed on the application.

In August, the Texas Water Development Board reported receiving 686 WSIG applications. Of those, 676 were submitted by the deadline and are currently under review, representing approximately $6.9 billion in requested funding. TWDB has roughly $1.038 billion appropriated for the program, so the demand is substantial.

TWDB also made an important distinction in its intake report: appearing on that list does not mean a project has been determined eligible, technically feasible, recommended for funding, or selected for an award. Review and prioritization are still underway.

If you need a refresher on the WSIG program, we previously broke down the funding opportunity and basic project requirements here: Texas HB500 WSIG Grant.

First: Watch Your Inbox

This may be the most immediate issue for applicants.

During review, TWDB can issue a Request for Information, or RFI, when it needs clarification, supporting documentation, or additional information. An applicant has three business days from the date the RFI is issued to provide a complete response. According to TWDB's August intake report, failing to respond within that window will cause the application to be deemed ineligible.

TWDB's current FAQ also says it will not issue administrative-completeness notices for WSIG. If an applicant is contacted to correct an error, that same three-business-day response period applies.

For a small city or district where one person wears six different hats, that's worth planning for.

Know who is watching the inbox, who the backup person is, and who needs to be pulled in quickly if TWDB asks for engineering, financial, property, environmental, or other project documentation.

What Happens After Review?

TWDB staff are currently reviewing timely applications for program requirements, project eligibility, prioritization, and other funding considerations. The adopted implementation timeline anticipates funding commitments beginning in Fall 2026, followed by closings from Winter 2026 through May 1, 2027.

Selection would not mean a check simply arrives in the mail.

TWDB's FAQ states that WSIG funds will be deposited into an entity-established escrow account at closing and released as applicable project milestones are completed. The agency has also begun publishing WSIG-specific checklists for engineering feasibility, plans and specifications, bidding, executed construction contracts, and project closeout.

In other words, the application may be finished, but the project file isn't.

Use the Waiting Period Wisely

This is also a good time to look at the project the way you would if TWDB called tomorrow and said it was moving toward funding.

Can you locate the application and supporting documents quickly? Who is responsible for a three-day RFI response? Are engineering and regulatory documents organized? If land acquisition is part of the project, do you know which parcels are still outstanding and whether ownership or title issues remain?

A few questions worth asking:

  • Can we quickly produce the records supporting statements made in the application?

  • Who owns the RFI response internally, and who is the backup?

  • Are design, permitting, environmental coordination, and agency approvals continuing on schedule?

  • If land or easements are involved, are acquisitions actually progressing?

  • Are there unresolved title, access, TxDOT, railroad, utility, or site-control issues?

  • If bidding is approaching, have WSIG requirements that could affect the bid documents been reviewed?

  • What still stands between this project and construction if funding is awarded?

For applicants that claimed ready-to-proceed status, this exercise is especially useful. TWDB defines that status around completed environmental coordination, acquisition of required land and easements, design, and permitting—not simply having a project that is far along on paper.

Check out our recent posting on: What Does “Ready to Proceed” Mean?

Don’t Put the Project on Hold Just Because the Application Is Pending

Waiting on a funding decision does not necessarily mean the project itself needs to stop moving.

Engineering may still be progressing. Permits or agency coordination may still need attention. Property acquisition may be underway. A city or district may be working through title issues, easements, bidding documents, board approvals, or other pieces of the project schedule.

In fact, continuing to resolve those items now may make the transition into funding and construction considerably easier if the project is selected.

But there is an important distinction between continuing to advance the project and assuming TWDB will reimburse everything spent while you wait.

TWDB does allow applicants to continue advancing project activities while funding decisions are pending, but applicants should be careful about assuming those costs will ultimately be reimbursed. Pre-award costs are subject to WSIG eligibility requirements, and the rules vary depending on the applicant and when the cost was incurred. Before advertising construction, executing contracts, or making a major expenditure based on expected grant reimbursement, it is worth checking the applicable TWDB requirements.

The practical takeaway isn't to rush ahead. It's to avoid losing several months simply because the application is under review.

Keep the engineer moving where appropriate. Keep resolving property and access issues. Keep permits and environmental coordination organized. And before making a major commitment based on expected grant reimbursement, make sure the applicable WSIG requirements have been checked.

The Bottom Line

The application deadline has passed. Now the useful work is less about changing the application and more about being prepared for what comes next.

Watch for TWDB correspondence. Keep the supporting project file accessible. And if funding does move forward, know what land, access, title, utility, or project-delivery work still has to happen before construction can.

🛠️ How Can TerraServ Help?

If Your Project Moves Forward, Is the Land Side Ready?

A funding commitment can move a project forward quickly, but easements, title issues, site acquisition, access, and utility conflicts still operate on their own timelines.

TerraServ works with Texas municipalities, districts, engineers, and infrastructure teams to research existing property rights, identify affected ownership, support easement and site acquisition, and coordinate land-related project issues before they become construction problems.

Have a WSIG project with property or utility questions still hanging out there? We're happy to compare notes.

📞 We love to chat, call us direct at: (512) 277-5497 or reach out to us at TerraServ@TerraServTX.com

Disclaimer: This article is provided for general informational purposes. WSIG eligibility, prioritization, funding commitments, and project requirements are determined by the Texas Water Development Board and may depend on the specific application and project. Applicants should rely on current TWDB guidance and their appropriate professional advisors.